How the Cross Border Connection impacts Cumbria landowners

D&R Director Paul Robinson <i>(Image: D&R)</i>
D&R Director Paul Robinson (Image: D&R)
This article is brought to you by our exclusive subscriber partnership with our sister title USA Today, and has been written by our American colleagues. It does not necessarily reflect the view of The Herald.

THE Cross Border Connection project is part of the Great Grid Upgrade, which will see infrastructure transmission lines crossing from Scotland through north Cumbria and connecting to the National Grid.

Details around the proposed routes have been long-awaited, but were finally announced in mid-October, giving North Cumbria landowners their first chance to see if it will affect their land.

What is the Cross Border Connection?

The Cross Border Connection (Galashiels to Cumbria ) is a joint development between SP Energy Networks (SPEN) in Scotland and National Grid Electricity Transmission (NGET) in England. The two parties are working closely on the project, with SPEN at least a year ahead of their English counterpart on consultations. Both will need to be aligned to progress to construction.

Scotland has been consulting on proposed routes for the Cross Border Connection for some time, but on the England side of the border, the project has only just got started. The initial consultation was announced on 15th October. It will run until 10th December and is the first opportunity for landowners and farmers to learn if the proposed infrastructure works will potentially affect their land.

Details of the work include installing a new 400 kilovolt (400 kV) substation in the Carlisle area, with connectivity to the existing electricity network and a new 400 kV overhead pylon line from the substation to the England–Scotland border.

What are the experts saying?

Paul Robinson, Director at Davidson & Robertson, a leading firm of Rural Surveyors and Consultants, said, “Scotland produces a considerable amount of renewable energy with an estimated 1 GB spare energy capacity that can be transferred to the English National Grid.

“We are already working with clients potentially affected by the SPEN project on the Scottish side of the border and have been waiting a long time to hear the proposed routes in England. Now that we have that initial detail, the landowners who may be affected will have a chance to provide feedback on the proposals.

“The proposed routes in England commence from the border at Kershope Forest and run down to Longtown and Carlisle, then Warwick-on-Eden and Wetheral. There is a long way to go before any route is finalised, but the announcement means landowners and farmers in the area are no longer in limbo.

“From our experience in Scotland, engaging a professional at the start of the process often saves time and money later on – and your agent can point out issues that landowners and land managers may not have considered. Once the proposed line route is approved, NGET will contact landowners, and from this point, your reasonable agency and legal fees are likely to be reimbursed by the operator as part of your compensation.

“Experienced Land Agents know how to check draft agreements, conditions, compensation, help prepare evidence and how it is going to impact you. Monitoring during construction may seem a long way off, but setting up a comprehensive Schedule of Accommodation Works (commitment register) at the start will make claims easier in the future and help mitigate losses.”

The consultation dates in Cumbria are as follows:

· Wetherall Village Hall Saturday, November 1 2-7pm

· The Rockcliffe Centre Carlisle Tuesday, November 4 2-7pm

· Wreay Village Hall Thursday, November 6 2-7pm

· Longtown Memorial Hall Community Centre, Saturday, November 8, 11am – 4pm.